Construction Projects

Active

Livonia Senior Wellness Center/Kirksey Recreation Center (Visit our project website to learn more)

  • New senior wellness center built northeast of The Rec. July 2024-Nov. 2025 (East FitHub relocated to MAC Gym Aug. 26-29, 2024.)
  • New West Gym built west of The Rec. July 2024-Aug. 2025.
  • Hubbard Road (south of Five Mile Road) temporary closure. Oct. 21-Nov. 3, 2024.
  • Conversion of Main Gyms into multi-purpose studios. July 2025-spring 2026.
    May 19-22: Indoor track closed. May 30: Full facility closure of The Rec. Weight equipment relocating across MAC Gym June 17 for roof replacement. No open gym July 21-24 while an electrical conduit is installed. The cardio area of the FitHub will be unavailable 9 p.m. July 25, but most of the equipment will be available in relocated space in the lobby until late July 27 when it is moved back. Aug. 8-9: The weight room in MAC Gym 1 closed. Aug. 11-26: Temporary Detour for flooring/ceiling installation.
    Aug. 29-30: Kirksey Recreation Center full closure. FitHub equipment to be placed throughout building during FitHub space remodeling.
    Sept. 2: Indoor track closes through at least November.

    Oct. 15: The new gym space opens on the west end of the building.



Kirksey Recreation Center Play Area

  • New outdoor play area next to splash pad. Began September 2025.

UPCOMING

Shelden Park

  • Park redesign (conceptual rendering may differ from final design). Summer 2025-Summer 2026.
    2025-6-10 Shelden Park Renderings Overview and Restrooms

Rotary Park

  • Pavilion 1 rebuild. Fall 2025.

COMPLETED

2025

Kirksey Recreation Center Splash Pad

  • Reconstruction. May-Oct. 2025.

Splash Pad Renovation Pic 1Splash Pad Renovation Pic 2

Rotary Park

  • Tennis Court sealing and recoating. May 2025.
  • Pavilion 2 roof replacement. July 2025.

Kirksey Recreation Center Locker Rooms

  • Men’s locker room and women’s locker room grout/tile work. July 2025.

Kirksey Recreation Center Leisure Pool

  • Renovate pool deck, hot tub siding, water slide maintenance. July-Aug. 2025.

Mies Park and Rotary Park

  • Outdoor Fitness Equipment Removal. Spring 2025.



2024

Bluegrass Park

Kirksey Recreation Center Inline Skating Rink

  • Resurfacing. June-Aug. 2024.

Ben Celani Play Area at Bicentennial Park

  • Pavilion addition. Spring 2024.

Mies Park




2023

Ben Celani Play Area at Bicentennial Park

  • Restroom. Fall 2023

Greenmead Historical Park 

  • Alexander Blue House roof.

Blue House roof replacement



2022

Ben Celani Play Area at Bicentennial Park

  • Inclusive Playground.
  • Senior Fitness Playground.
  • Parking lot redesigned replacement.

Ben Celani Play Area 2022 Redesign


Greenmead Historical Park - Bungalow roof 

Clements Circle Park - Pavilion replacement 

Country Homes Park - Playground replacement

2022-5-23 Country Homes Playground 22022-5-23 Country Homes Playground 1